20210823_140425.jpg
20210824_095423.jpg
20210831_155941.jpg
20210915_092525.jpg
20210916_101419.jpg
20210916_164510.jpg
20210922_124812.jpg
20210922_124800.jpg

90m2 Clay tile re-roof

Renewed failing structural timber work and lead valleys. 

Asbestos slate strip and removal

Natural slate installed with leaded hip and ridge details. 

20210719_113953.jpg
20210719_104023.jpg
20210719_113923.jpg
20210622_111840_edited.jpg
20210611_131812.jpg
20210618_103913.jpg
20210614_104103.jpg
20210619_114651.jpg
20210621_123247.jpg
Double re-roof - Clay tile with ornamental ridge.
20210414_133751.jpg
20210512_111011.jpg
20210519_105826.jpg
20210409_095612.jpg
20210508_101959.jpg
20210421_111452.jpg
20210517_101910.jpg
20210519_094354.jpg
20210519_122702.jpg
20210519_122718.jpg

Here, we widened the existing undersized coping stones by mechanically fixing timber. The coping stones were then mechanically fixed into place too, before being over clad with code 4 sheet lead. All 66 metres of them.

Sadly for such a new development, there's lots more to do here
30 raymend 3.jpg
30%20raymend%201_edited.jpg
30 raymend 2.jpg
Roof, masonry, lead and timber work repairs, Bristol.

Here we have undertaken extensive works to two adjoining properties. Works included:

>Repair of natural and reconstituted coping stones to both properties.
>Installation of Lead sheet cladding to all coping stones and abutments.
>Repairs to all roof elevations, including stripping and reinstatement of ornate clay ridge. 
>Supply and installation of a new bay roof in code 6 sheet lead. 
>Refurbishment of timber fascia and soffit to both properties.
>Supply and installation of a new rainwater guttering system to both properties.

Whithy close Collage2.jpg

 

Small plain tiled roof refurbishment in Westbury on Trym, Bristol. 
Whithy close Collage1.jpg

 

Stripped and reinstated coping stones with new abutment lead cover flashing.
Westbury on Trym, Bristol. 
west lea collage.jpg

 

Full clay tile roof refurbishment in Weston village, Bath. Complete with newly refurbished soffit, uPVC clad fascia and new 112mm half round guttering. 
This was a tricky one to get completed over the January period, as all work was completed traditionally which meant that we were hampered by the cold and wet weather!
Our client is delighted with the transformation, and for less than quoted. So in the end, all is well and we are really pleased to have been chosen to deliver this work.
IMG_20200929_230354_478.jpg

 

LEAD VALLEY REPAIR - Fishponds, Bristol.
As an alternative to costly full refurbishment, this defective lead valley was repaired.
 
Splits had occurred in the esxisting oversized lead, due to thermal expansion and contraction.
The existing splits have now been overlaid with new pieces of code 4 lead sheet, extending the life of the existing valley construction for years to come. 
Collage 2020-12-18 18_20_27.jpg

 

 

Supply and installation of lead capping to coping stones - Bedminster, Bristol.
These defective coping stones had been allowing for ingress for years, following several failed attempts at repair. To ensure any ingress issues were permanantly cured, we supplied new code 4 lead capping to the entire run of coping stones, ensuring new cover flashings were chased into the chimney at the abutments. 
Collage 2020-12-19 10_24_15.jpg
Replacing ridge tiles - Bedminster, Bristol.
Stripping and relaying existing concrete ridge tiles, with additional cover flashings to ensure correct coverage can be achieved.
These ridge tiles had been laid with an inadequate lap by others, and had subsequently been repaired using a cement mortar. 
To ensure these ridge tiles would provide adequate coverage to the tiles either side, new code 3 lead cover flashings were installed beneath the reinstated ridge tiles.
Collage 2020-12-19 10_31_18.jpg

 

Leadwork, Bath.
Here we supplied new code 4 lead cover flashings, to this large glazing unit on a property in Bath.
Collage 2020-12-18 18_39_43.jpg

 

Chimney take down and partial rebuild - Bedminster, Bristol.
Here, a defective chimney was partially dismantled and rebuilt, before being weatherproofed with new lead work and a cement mortar capping. New render was then applied to provide additional long term weatherproofing. 
Collage 2020-11-24 17_54_32.jpg

 

 

 

Small roof refurbishement - Henleaze, Bristol.
Instalaltion of lead cover flashings to the front gable barge boards.  
Collage 2020-11-24 17_51_10.jpg

 

 

Bedminster, Bristol.
Installation of lead cover flashings to barge boards and inside roof tile abutment, incorporating new uPVC barge boards in anthracite grey. 
IMG_20201026_143146_375.jpg

 

 

 

 

Bedminster, Bristol.
Installation of lead cover flashings to roof verge and inside roof tile abutment.
Collage 2020-11-24 18_03_33.jpg

 

 

 

 

Weston village, Bath.
New lead back gutter to this chimney.